Production Schedule
Home / Analysis / Production Schedule
21 May 2026  |  Morning Shift
Production Batches
Jadwal Batch — 21 May 2026
3 In Progress 2 Pending 1 Completed
Batch ID Product Recipe Line Planned Start Planned End Actual Start Actual End Target (units) Output % Status Actions
B-2605-001 PRD-A RCP-001 Line 1 06:00 14:00 06:05 1,440
62%
In Progress ✎ Edit
B-2605-002 PRD-A RCP-001 Line 1 06:00 14:00 06:00 1,440
38%
In Progress ✎ Edit
B-2605-003 PRD-B RCP-002 Line 1 10:00 18:00 960 Pending ✎ Edit
B-2605-004 PRD-C RCP-003 Line 2 06:00 14:00 06:00 1,440
55%
In Progress ✎ Edit
B-2605-005 PRD-A RCP-001 Line 2 06:00 14:00 06:10 1,440
68%
In Progress ✎ Edit
B-2605-006 PRD-B RCP-002 Line 2 10:00 18:00 960 Pending ✎ Edit
B-2604-010 PRD-A RCP-001 Line 1 20 May 06:00 20 May 14:00 20 May 06:02 20 May 14:08 1,440
98%
Completed
Production Schedule Revision History
Riwayat Revisi Jadwal Produksi — Batch Schedule Revision
Batch ID Revision # Changed By Changed At Reason / Alasan Field Changed Old Value New Value
B-2605-002 Rev 2 Supervisor A 21 May 07:00 Machine down — U-001 Planned End 14:00 16:00
B-2605-003 Rev 1 Planner B 20 May 16:30 Raw material delay Planned Start 08:00 10:00
B-2604-010 Rev 1 Supervisor A 19 May 09:15 Recipe update — new cycle time Recipe RCP-001 v1 RCP-001 v2
+ Add Production Schedule
Tambah Jadwal Produksi Baru
✎ Edit Schedule — B-2605-002
Ubah Jadwal Produksi · PRD-A · Line 1 · In Progress
Wajib diisi — akan dicatat di Schedule Revision History